Case
13 - Pool built in the spring / summer of 2007 near Monflinquin
in Lot-et-Garonne for Mr and Mrs Bull
Well - this is the biggest
pool that we have built and it was one big big big problem!
It did not look too bad
when we started - you can just see the outline of the pool location
on the first picture.
The second two pictures
show what the site was really like. We had to install a 50 metre
long large diameter drain just to get the site dry enough for the
digger to move around the site.
Eventually we got the
foundations finished as you can see from the fourth picture.
The pool and walls are
built on consolidated fill and so the foundations of both the walls
and the pool are highly reinforced.
We also had to build the
2.5 metre high curved retaining wall in reinforced concrete filled
hollow concrete blocks. At one end of the wall we built an underground
plant room as well as a long flight of suspended concrete steps
over 4.5 metres high.
The walls were covered
with Orsol concrete facings and the pool was equipped with a floating
safety cover that is mounted on submerged motor driven roller.
The project took about
6 months to build and the final contract value was about 120,000
euros HT.