If
you want a pool for use in the summer of 2007 please contact us as soon
as possible as our installation slots for this autumn and next spring
are now filling up rapidly
0546
48 37 99
To
contact us please telephone our French number above or click on Contact
Form to tell us your requirements
CASE
STUDIES
All
the owners of the Case Study pools can be contacted for a reference
Case
Study A
Client
- Retired office fitting-out contractor
Location
- 15 kms south of St Jean d'Angely in Charente-Maritime
Pool
specification - 7 x 5 m concrete block infill reinforced concrete
walls with hopper
Built
- Spring 2005
The
issues
The
weather was very wet throughout the construction of this pool
and this delayed completion.
An
existing pig sty needed to be demolished and the pool was to be
built very close to the existing barn. The client wanted to keep
the stone for future extension work. There is a slope of 700 mm
across the site and this required the erection of a retaining
wall. The pool paving has to slope away from the pool so that
rainwater is not shed into it. This creates a potential problem
of damp in the barn wall - this was avoided by the installation
of a land drain along the foot of the wall. The drain from the
kitchen sink also crossed the site and this was diverted into
a new fosse around the back of the barn in the pictures - this
was also built by us
click
on thumbnail for bigger picture
(the
pictures are large and may be slow to load)
The site
before we started - note the small barn to be demolished
The trees,
hedges and barn have gone
The pool
has been set out and excavation has commenced
Most
of the pool has been excavated down to level and the concrete
blocks for the walls have been delivered
Part
of the wall foundation has now been cast - note the starter
bars for the wall reinforcement
The foundation
is complete and the erection of the walls has commenced
Erection
of the wall continues with the first layer filled with concrete
down one side of the pool
Erection
of the wall continues - note that the main drain has been
installed and surrounded in concrete
The walls
are just about complete
The pool
floor is ready for screeding - note that the pool is being
built on quite solid limestone rock - this allows the use
of a non-reinforced screed floor
The Roman
end has been installed and concreted in
The narrow
reinforced concrete slab on the right hand side of the pool
is ready for concreting - note that the reinforced concrete
slab will span the gap between the pool wall and the edge
of the excavation that has been backfilled
The slab
is concreted around two sides of the pool - this will support
the paving slabs and ensure that there is no settlement of
the slabs. Note the land drain that protects the existing
wall from getting damp - the paving will shed rain towards
this drain
The screed
to the floor is just being finished - this is always a key
task as it has to be done without rain falling on it - we
now cover the pools when we do this to avoid rapid drying
under the hot sun or rain damage
All the
concrete work around the pool is now complete
As this
pool has concrete block walls they need to be rendered. This
is a three stage process, the screed rails, the scratch coat
and the finish coat - here the scratch coat has been completed
We are
nearing completion - note that the margelles (coping stones)
and the dalles (paving flags) are of the same make and have
a common joint pattern - the pool needs to be built exactly
to the right size to allow this
The paving
has been grouted and the alarm installed
The pool
is totally complete with the heat pump installed. The client
will install his spa on this side of the heat pump to hide
the pipework.
A view
from the other end looking at the heat pump. The pool users
will be able to stand in front of the fan to cool themselves
down on hot days
Case
Study B
Client
- Retired bank manager
Location
- About 20 kms to the east of Nontron in the northern Dordogne
Pool
specification - 11 x 5.5 m concrete block infill reinforced
concrete walls with hopper
Built
- Late Spring 2005
The
issues
The weather was awful during the construction of this pool
- as can be seen from some of the photographs. Access to
this pool site was difficult and the wet weather made the
ground so soft that we could not get heavy materials delivered
to pool area - so everthing had to be barrowed into the
site. We knew that there were various drains crossing the
site and that a new soakaway would be required.
The
most significant issue was that there is a 1 metre slope
from one corner of the pool to the opposite corner and a
0.5 m slope across the short end containing the Roman Steps
- hence the finished level of the pool needed to be carefully
considered so that the garden looked good and all the future
grass slopes are mowable.
During
the course of the work the weather was so bad that we had
to build butresses to support the decking around the pool
because we had no suitable material to backfill with.
The site
- note that it looks quite level - but there is a slope from
the top left hand to the bottom right of nearly a metre
The wall
foundation excavated down to level with some shutters installed
- we were already knee deep in mud. We decided to cast the
foundation before we excavated the pool to level
The weather
just got worse and worse - we cut through the drain that you
see and just afterwards the heavens opened - and the drain
was from the property roof!. In the end we had to dig and
put blinding concrete down straightaway - just to get a solid
base to work on
Part
of the wall foundation has now been concreted - this site
was very difficult because of the silty sandy clay sub-soil
- if it had been limestone rock the rain would not have been
much of a problem
The foundation
is complete!! - this has taken us two weeks - in a normal
circumstance the entire pool structure would now be finsished
and ready to fill with water
The walls
are up and ready to fill with concrete
We had
to build these butresses to support the outside wall of the
pool and the decking - purely because of the terrible ground
conditions - we worked right through whether it was raining
or not - I have never been so cold and wet!
It was
impossible to finish the landscaping - we had to come back
a month afterwards when it had dried out. Note the land drain
that runs around the outside of the pool wall and through
the butresses
What
a mess!! - compare this with the shot of the garden before
we started - it is impossible not to make a mess like this
when it rains so much
Its dried
out a bit and we are managing to excavate for the sub-pool
drainage under the hopper
The sub-pool
drainage under the hopper - note the suction pipe is inserted
into black slotted pipe wrapped in geotextile so that it does
not get clogged up. The whole drain is also wrapped in geotextile
for the same reason
We had
to put a drain under the flat end of the pool because of the
very poor ground conditions
The drains
are in place and covered with concrete
The pool
floor has been screeded and the Roman End is now being installed
Note
that the vertical screed rails for the scratch coat have been
completed
The Roman
End has been concreted in and the scratch coat to the wall
render has been completed
The render
to the walls is complete and the liner lock is in place
The underlay
on the floor is in place and the joints taped up
The liner
being installed
Water
is going into the pool - note the vacuum cleaner that sucks
the air out from under the liner to get rid of the trapped
air that causes creases
This
shows how the liner is supported across the Roman End before
being cut to shape - and it is still raining!!!!
The summer
cover is on - client was heating the pool water up and the
margelles are being installed. Note the white tube that is
connected to the under pool drainage - if this pool is ever
emptied a pump will need to be connected to this tube and
run until no water emerges
It is
just about finished and we have managed to do the landscaping
at last
It is
finished at last - what a saga
Another
view with the summer cover in place
Another
view with the winter cover in place
Ready
for a party!!
Another
view
Our client
was very patient with us throughout the trials and tribulations
of this project - it took as three times as long as we said
it would and the only extra that we charged was for the butresses
and the sub-pool drainage and a new soakaway for the roof
drainage
Case
Study C
Client
- Investment banker
Location
- In Argenton-sur-Creuse in Limousin
Pool
specification - 12 x 5.5 m polystyrene block infill reinforced
concrete 1 m high walls with 1.3m deep hopper
Built
- Summer 2005
The
issues
The
client was very concerned that we should minimise damage
to his parkland style garden. The site of this pool sloped
about 600 mm from one corner to the other.
We
knew that there was a drain crossing the site to the sewer
in the road, but we did not know that the roof drainage
from the large house also crossed the site and discharged
into a large concrete lined pond. The client wanted the
pond to be filled in and the mairie was happy for us to
do so. Hence the landscaping included filling the pond,
getting the slopes across the parkland to look gradual and
natural and to build a large soakaway in the filling to
the old pond to receive the roof drainage.
When
we excavated for the pool we found that the entire pool
area consisted of filled ground and when we excavated for
the hopper the hole immediately began to fill with water
even though the weather had been very dry for weeks. We
installed sub-pool drainage as normal and also built hopper
area of the pool - where the ground was worst - in reinforced
concrete.
Start
of the topsoil strip - this was a beautiful garden at the
bottom of a big hill-side
The house
was fantastic as well - I think the pool may have been better
if much closer to the house - but the client wanted the location
because it maximised sunlight on the pool in a quite heavily
wooded garden
Getting
down into the ground - the fall across this site was about
800 mm from the top right to the bottom left side of the pool
Ugh!!
- the ground is fill and not natural soil
The wall
foundations were reinforced with plenty of bars because they
are on fill
This
is all fill as well - and even worse there is water seeping
in the middle of June
Sub-pool
drainage is required with the whole lot wrapped in geotextile
all as in Case Study B above
Concrete
has now been placed over the drain to stabilise the excavation
Shaping
the bottom of the pool and the hopper
The hopper
had to be formed in reinforced concrete because of the filled
ground
Reinforced
concrete hopper complete and polystyrene block walls erected
Detail
of the polystyrene block walls with reinforcement and ready
for concreting
This
is me fixing the return pipes through the Roman End
Screed
is complete and ready for the liner
The liner
is installed and the pool is being filled - note the wide
reinforced concrete slab in the foreground ready to receive
the dalles (paving slabs)
Margelles
and some slabs installed - not the matching joints
It is
finished - but not full up - we had a big problem getting
the seal around the Roman End installed properly - and had
to drain down a couple of times!!
The paving
around the Roman End
The decking
- the mixture of paving and decking works well when the pool
is away from the house in the garden because the visual impact
is softened
The decking
again - not that it is lifted up above the ground so that
it does not rot (the timber is treated as well and we use
special non-rust screws)
Heat
pump and buried pump and filtration unit. This will need
some planting around it to hide the visual impact.The client
is delighted with his pool and the only extras were for,
the reinforced concrete hopper and the construction of a
new soakaway for the roof drainage that was cut off by the
pool installation
Interested
in a licence to build our pools? - Please
contact us if
you have been operating a successful building or pool business in
France for at least 2 years - To apply click on